The first stage of the extended production and distribution area of La Lorraine in Kladno was completed in accordance with our design and project

The design of 40 m high cold storage facility with the floor plan of 130m x 45m was a real challenge for us. The high-tech production and storage facility is completed and it will be commissioned soon. It is the first stage of extension of La Lorraine production and distribution area in Kladno. All fire resistant structures meet hygienic requirements imposed on construction materials. At the same time it was necessary to design buildings with the view of extension in future. Energy efficiency and overall energy savings are obvious in this type of project. New administrative facilities and well-arranged in-house routes for employees will be prepared in next stages.